MIL-DTL-62739A(AT)
6.3 First article. When requiring a first article inspection, contracting documents should
provide specific guidance to offerors. This guidance should cover whether the first article is a
first article sample, a first production item, or the number of test items. These documents should
also include specific instructions regarding arrangements for examinations, approval of first article
test results, and disposition of first articles. Pre-solicitation documents should provide
Government waiver rights for samples for first article inspection to bidders offering a previously
acquired or tested product. Bidders offering such products who wish to rely on such production
testing must furnish evidence with the bid that prior Government approval is appropriate for the
pending contract.
6.4 Conformance inspection. Affordable conformance inspection with confidence varies
depending upon a number of procurement risk factors. Some of these factors include: Contractor
past performance, Government schedules and budget, product material and design maturity,
manufacturing capital equipment and processes applied, the controlled uniformity of those
processes, labor skill and training, and the uniformity of measuring processes and techniques.
During the solicitation, contracting documents should indicate those tests desired from table II
and their designated frequency based on a risk assessment for the procurement.
6.5 Historical data. Historically, ATPD 2148, dated 9 March 1988, was superseded by
MIL-P-62739(AT).
6.6 Subject term (key word) listing.
Real time clock
Simplified Test Equipment/Internal Combustion Engine - Reprogrammable (STE/ICE-R)
Vehicle test meter (VTM)
6.7 Changes from previous issue. Marginal notations are not used in this revision to
identify changes with respect to the previous issue due to the extent of the changes.